Quick answer
The ADB-mandated process by which executing agencies analyse the market, assess risks, and select procurement methods for a project before issuing any tenders, resulting in a documented strategy that shapes the entire procurement programme.
Strategic Procurement Planning is the structured analytical process that ADB requires executing agencies to complete before procuring goods, works, or services under an ADB-financed project, producing a documented strategy that links project objectives to appropriate procurement methods, packaging decisions, and market engagement approaches.
What is Strategic Procurement Planning?
The 2017 adb-procurement-policy introduced strategic procurement planning as an explicit requirement because previous approaches often resulted in procurement methods chosen by habit rather than market reality. The process asks executing agencies to assess the supply market for each contract package, consider the risk profile of the procurement, analyse whether international or local competition is realistic, and then select the method, packaging, and timeline that best serve the project's objectives within the core-procurement-principles.
The output is a documented procurement strategy that feeds directly into the project's procurement-plan, the public document that lists all planned contracts, their estimated values, and their procurement methods. ADB staff review the strategic procurement plan as part of project preparation, and significant deviations from it during implementation require ADB's agreement. The process explicitly allows for market sounding, meaning executing agencies and ADB can engage with potential suppliers informally before issuing formal procurement documents, to test assumptions about market capacity and pricing.
Why Strategic Procurement Planning matters for bidders
Market sounding conducted during strategic procurement planning is one of the few legitimate opportunities for suppliers to influence how a procurement is structured before it goes to tender. When ADB or an executing agency invites industry input, suppliers who respond with substantive market information, realistic pricing benchmarks, and honest assessments of what the contract scope requires can shape packaging decisions in their favour. Firms that are already registered in cms and active in the relevant dmc are more likely to be contacted for market soundings. Monitoring ADB project approval announcements and then reaching out to the executing agency and ADB task team during project preparation is the way to participate in this early stage.
FAQ
Is the strategic procurement plan a public document?
The strategic procurement plan itself is typically an internal ADB-borrower working document. Its outputs, including the procurement method and package structure, flow into the procurement-plan, which is published on ADB's project portal.
Can the procurement strategy be changed after it is approved?
Yes, but changes require ADB's agreement, particularly if they affect procurement methods, packaging, or contract values significantly. The intent is that the strategy is stable enough to give the market predictable signals.
What is a market sounding in this context?
A market sounding is an informal consultation where ADB or the executing agency seeks supplier input on pricing, technical requirements, or market capacity before finalising procurement documents. It is not a tender and creates no procurement obligation.
How Bidovate helps
Bidovate puts Strategic Procurement Planning to work inside your capture and proposal workflow.
Anticipate ADB procurement approachesSee Bidovate in action
Book a demo and we will show you the platform using your actual contract data.
Related terms
ADB Procurement Policy (2017)
The Asian Development Bank's governing framework for all project procurement, adopted in 2017, that replaced the previous guidelines with a principles-based approach centred on value for money and fit for purpose.
ViewProcurement Plan
The rolling 18-month schedule that a World Bank implementing agency publishes listing every planned contract, its method, estimated value, and timeline.
ViewCore Procurement Principles
The five foundational principles, economy, efficiency, fairness, transparency, and integrity, that underpin the ADB Procurement Policy (2017) and guide all procurement decisions on ADB-financed projects.
ViewCountry Partnership Strategy (CPS)
The Asian Development Bank's multi-year strategic framework for a specific developing member country, setting the sectors, thematic priorities, and lending targets that drive the project pipeline for that country.
ViewAdvance Procurement Action
ADB's permission for a borrower to begin certain procurement steps before a loan or grant is formally approved, reducing the gap between project approval and contract award on time-sensitive infrastructure projects.
View